Monday, June 23rd & Wednesday, June 25th
All trees will be removed on all roads on the dates above

Battle Hill Avenue
Curb – sidewalks – aprons - 6/24/2014 – 7/03/2014
Milling & paving to follow

Hawthorne Avenue
Curb / sidewalk/ aprons - 7/07/2014 – 7/18/2014
Milling & paving to follow

Lyons Place
Curb / sidewalk / aprons - 7/21/2014 – 7/25/2014
Milling & paving to follow

Short Hills Avenue
Curb / sidewalk / aprons - 7/28/2014 – 8/04/2014
Milling & paving to follow

Redwood Road
Curbs / sidewalk / aprons - 8/05/2014 – 8/08/2014
Milling & paving to follow

Remer Avenue
Curbs / sidewalk / aprons - 8/11/2014 – 8/15/2014
Milling & paving to follow